New pools are constructed from scratch.

Quotes will be provided once certain information is obtained from prospective clients. On acceptance of quote we will go to the next stage which is planning and marking. Once marked out and checked by customer we will begin digging and preparing the hole for concreting. Reinforcing is installed into completed hole before concrete is poured, we use 30mpa ready mix (pool mix).

Over the next two weeks all the finishing touches are installed, coping, mosaics, pumps, filters, piping, db boxes and water features etc. After two week either marble lite or fibre glass is installed. We are now ready to fil the pool.

Building proces takes +/- 4 weeks.